Landesbetrieb Liegenschafts- und Baubetreuung Niederlassung Trier
Rahmenterminplan JVA Wittlich: Sanierung alte Männeranstalt inkl. vorgezogene Maßnahmen
SAP: 700 20 1011
| 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | |||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | |||||||||||||||||||||
| Projektvorbereitung | Projektvorberei se Teil-HU-Bau 9.2025 An A : Herstellung Ba AFU-Ba rung vorgezogen utzungsbeginn | tung Schadstoffsanier Vorlag 1. Teil 2. Teil 3. Teil 4. Teil passung QBA, Ei bgabe HU-Bau „f Prüf Abg ufeldeinfriedung u inkl. Vergaben e Maßnahme H Halle 33 / 34 (03 | ung | taffelt) gen | Ne | ubau Geb. 04 B | esucherzentrum | / Umbau Geb. 0 Ausführung Geb | 2 Pforte . 01 und Außen Rückb | anlagen Teil 1 au Sicherheitsb Ausfüh Ü | ereich Ausführung Fa und Außenanla rung Stellplätze bergabe zur IBN Inb Nu | ssade Giebel B gen Teil 2 Süd (27.02.2032) etriebnahme de tzungsbeginn (2 | s Nutzers 8.05.2032) | |||||||||||||||||||||||||||||||||||||||||||||||
| Projektvorbereitung / Vergabeverfahren | 25.10.2018 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 01.10.2026 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Schadstoffkatas gskonzept und | ter, Kosten Vorlage LBB K | Erstellu 24) ung LPH02 vor | Planung Pr Rückbau“, ng LBB Kostenpr | obesanierung u Erstellung Teil- ognose Sanieru Bea 6.03.2025 | nd „Schadstoffsa HU-Bau inkl. Gen ng alte Männera rbeitung Vorpla | nierung u. ehmigung nstalt (SAM) nung LP02 Sani | Ge nderung Haftrau die MS2 vor Min | nehmigungspha mgrößen“ isterien am 29.0 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
| erung Alte Männ Erstellung Machb Vorstellung | eranstalt arkeitsstudie „Ä Machbarkeitsstu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Vorlag 1. Teil 2. Teil 3. Teil 4. Teil | e der HU-B "Baufeld / „Schadsto „Geb. 02, "Alte Männ | au erfolgt Sicherheits ffsanierung Geb. 04, A eranstalt | im Rahme abtrennun und Rück ußenanlag Geb. 01" bz | n von Teil- g": Geneh bau“, Vorla en, Stellplä w. "final", | HU-Bauen: migung seit ge bei LBB | ens FM er : vrs. End ge bei LBB | folgt (22.05 e März 202 : 29.06.20 2.2026 | .2025) 6 26 – 13.10 | .2026 (ges | taffelt) | ||||||||||||||||||||||||||||||||||||||||||||||||||
| ostenprognose | SAM beim FM (fi Vor | nal am 06.08.20 stellung Vorplan | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| tze“, Vorla Vorlage be | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Ministerien am 0 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| i LBB: 04.1 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| narbeitung Ände inal“ an LBB (04 ung HU-Bau San abe HU-Bau „fin G B und Rückbau B : Probesanierun alle 33 / 34 und .09.2026) | rungen in LP02, .12.2026) ierung alte Män al“ bei FM (25.0 enehmigung HU eauftragung / G Durchfü rücke JSA g, Schadstoffsan | Bearbeitung de neranstalt und Z 2.2027) -Bau durch Mini enehmigung HU- hrung ö. R. Verf ierung und Rüc | r LP03 und Erste usammenstellun sterium inkl. Ko Bau Sanierung ahren (Zustimm Hinw nac kbau | llung HU-Bau S g mmentierungsph alte Männeranst ungsverfahren) | AM ase, Abschlussb alt (04.06.2027) | esprechung, Nac | hbereitung der | HU-Bau-Unterla | ||||||||||||||||||||||||||||||||||||||||||||||||||||
| AFU-Ba | u inkl. Vergaben | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Hinw nac | eis: Begin h Zusamme | n AFU-Bau nstellung | Sanierun und Vorlag | g alte Män e der HU-B | neranstalt 3 au bei LB | Monate B | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Ausfüh N | AFU-Bau i Schadstoffsa | nkl. Vergaben: S nierung Geb. 01 | anierung alte M | änneranstalt | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Kammer (Kamm g inkl. Maß g (NEA) N | er storniert) nahme Netzersa utzungsbeginn N | tzanlage (NEA) etzersatzanlage | (03.09.2027) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| P | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Vorbereitu | ng + Planung (NEA | ) | AFU-Bau + Verg | abe (NEA) | Ausführun Vorbereitun | g inkl. g (NEA) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| robesanierung u | nd vorgezogene | Schadstoffsanie | rung | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Abbruch + b. 004 (30.06.2 nung u. Änderu ung (15.10.202 | Schadstoffsanie 026) ng der Schließun 6) | rung: Kartoffelk g | eller, Kokskeller | , Verbindungsga | ng, Geb. 04 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Auszug Kamm | er und Werbetr Erstellung S Beginn Si | iebe JSA aus Ge icherheitsabtren cherheitsabtrenn | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| I | nbetriebnahme, | Abnahme- und | Übergabebegeh Ausführ | ung, Einweisung ung Stellplätze N | , Restarbeiten ord | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 20 | 23 | 20 | 24 | 20 | 25 | 20 | 26 | 20 | 27 | 20 | 28 | 20 | 29 | 20 | 30 | 20 | 31 | 20 | 32 | |||||||||||||||||||||||||||||||||||||||||
| Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec | Jan - Mar | Apr - Jun | Jul - Sept | Oct - Dec |
| Planung | |
|---|---|
| Erstellung Schadstoffkataster, Entsorgungskonzept und Kosten Planung Probesanierung /Schadstoff- sanierung, Teil-HU-Bau inkl. Genehm. | 15.08.2023 – 31.03.2024 |
| 12.09.2025 – 09.06.2026 |
| Erstellung LBB Kostenprognose Sanierung alte Männeranstalt | 20.09.2023 |
|---|---|
| 06.08.2024 |
| Bearbeitung Vorplanung LP02 Sanierung Alte Männeranstalt | 16.07.2024 |
|---|---|
| 06.03.2025 |
| Erstellung Machbarkeitsstudie „Änderung Haftraumgrößen“ | 21.03.2025 |
|---|---|
| 17.09.2025 |
| Anpassung QBA, Einarbeitung Änderungen in LP02, Bearbeitung der LP03 und Erstellung HU-Bau SAM | 30.09.2025 |
|---|---|
| 04.12.2026 |
| Prüfung HU-Bau Sanierung alte Männeranstalt und Zusammenstellung | 07.12.2026 |
|---|---|
| 24.02.2027 |
| Genehmigung HU-Bau durch Ministerium inkl. Abschlussbesprechung | 26.02.2027 |
|---|---|
| 04.06.2027 |
| Durchführung ö. R. Verfahren (Zustimmungsverfahren) | 13.05.2027 |
|---|---|
| 13.08.2027 |
| Ausführungsvorbereitung | |
|---|---|
| AFU-Bau inkl. Vergaben: Herstellung Baufeldeinfriedung u. Rückbau Brücke JSA | 16.06.2025 |
| 15.05.2026 |
| AFU-Bau inkl. Vergaben: Probesanierung, Schadstoff- sanierung und Rückbau | 01.11.2025 |
|---|---|
| 10.11.2026 |
| AFU-Bau inkl. Vergaben: Sanierung alte Männeranstalt | 11.05.2027 |
|---|---|
| 31.10.2028 |
| Ausführung | |
|---|---|
| Ausführung vorgezogene Maßnahme Halle 33 / 34 und Kammer | 17.06.2024 |
| 12.08.2026 |
| Ausführung Netzersatz- anlage (NEA) | 30.06.2025 |
|---|---|
| 03.09.2027 |
| Probesanierung und vorgez. Schadstoffsanierung Schadstoffsanierung Geb.01 | 05.05.2026 – 28.07.2026 |
|---|---|
| 25.11.2026 - 16.10.2028 |
| Abbruch + Schadstoffsanier. Kartoffelkeller, Kokskeller, Verbindungsgang, Geb. 04 | 12.05.2026 |
|---|---|
| 27.04.2027 |
| Neubau Geb. 04 Besucher- zentr. / Umbau Geb. 02 Pforte | 21.03.2028 |
|---|---|
| 13.12.2030 |
| Erstellung Sicherheitsabtrennung u. Änderung der Schließung | 07.04.2026 |
|---|---|
| 14.10.2026 |
| Ausführung Geb. 01 und Außenanlagen Teil 1 | 08.06.2028 |
|---|---|
| 26.06.2031 |
| Inbetriebnahme, Abnahme- und Übergabebegehung, Einweisung, Restarbeiten | 27.03.2031 |
|---|---|
| 02.10.2031 |
| Rückbau Sicherheitsbereich | 06.10.2031 |
|---|---|
| 13.11.2031 |
| Ausführung Fassade Giebel B und Außenanlagen Teil 2 | 14.11.2031 |
|---|---|
| 15.03.2032 |
| Ausführung Stellplätze Nord Ausführung Stellplätze Süd | 30.01.2031 – 27.06.2031 |
|---|---|
| 14.11.2031 – 13.02.2032 |
| Inbetriebnahme des Nutzers | 01.03.2032 |
|---|---|
| 27.05.2032 |
LBB Competence Center
JVA Wittlich, Sanierung alte Männeranstalt
Projektsteuerung
Grundlage: Steuerungsterminplan 20.03.2026
Stand: 20.03.2026